Step 10: Maintain Activity Overlays


Using this procedure an authorized worker, usually a support co-ordinator or system administrator, constructs groups of activities called "overlays" which are used by the case planning function.


.
CS3090?2 Build Activity Overlays 3/13/97
INPUT 13:52:34

Provider.. SI Services Intake Worker....... TOMCOX
??????????????????????????????????????????????????????????????????????????????

Service..................* APSIN
Process..................* ..................................................
: CS4080?1 Lookup Process :
: Process Name... ______________________________ :
: Service Code... APSIN :
: _S__Svc___Prcs__Name__________________________ :
: _ APSIN APSSR Screen Report :
: _ APSIN REFDA Refer Report to Another Agency :
: _ APSIN REFNO Determined Not Referred :
: _ APSIN REFOA Refer Report to Another Agency :
: _ APSIN REFY APS Report Determined Referred :
.

.
1 ? Create a New Activity Overlay
2 ? Work With an Existing Activity Overlay
3 ? View an Existing Activity Overlay
4 ? Delete an Existing Activity Overlay

.

.
CS3090?2 Build Activity Overlays 11/16/97
INPUT 16:04:46

Provider.. CWS ZZZ Nursing Home Worker....... CWS
??????????????????????????????????????????????????????????????????????????????

Service..................* _____
Process..................* _____

.
CS3090?3 Build Activity Overlays 11/16/97
CREATE 16:07:35

Provider.. CWS ZZZ Nursing Home Worker....... CWS
Service Children Foster Care Process 5094 Form
??????????????????????????????????????????????????????????????????????????????
Activity to be Performed..* _____
Activity Priority.......... 1
1 = Must Do
2 = Should Do
3 = Can Do
Displacement in Days....... ___
Displacement Type.......... W W=Working Days, C=Calendar Days
Print Activity Ticket?..... Y Y=Yes, N=No
Document ID...............* ____________
Comment.................... ______________________________
Reoccuring Type Activity?.. N Y=Yes, N=No
Activity Use Code.......... N N=Normal, P=Pre?requisite, D=Dependent
Pre?Requisite Activity....* _____

Last Changed............... 11/16/97 By CWS

Enter *F8=Lookup F9=Std Codes F12=Previous


.
.
CS3090?3 Build Activity Overlays 11/16/97
CREATE 16:09:23

Provider.. CWS ZZZ Nursing Home Worker....... CWS
Service Children Foster Care Process 5094 Form
??????????????????????????????????????????????????????????????????????????????
Activity to be Performed..* F5094
Activity Priority.......... 1
1 = Must Do
2 = Should Do
3 = Can Do
Displacement in Days....... __1
Displacement Type.......... W W=Working Days, C=Calendar Days
Print Activity Ticket?..... Y Y=Yes, N=No
Document ID...............* ____________
Comment.................... ______________________________
Reoccuring Type Activity?.. N Y=Yes, N=No
Activity Use Code.......... N N=Normal, P=Pre?requisite, D=Dependent
Pre?Requisite Activity....* _____

Last Changed............... 11/16/97 By CWS

Enter *F8=Lookup F9=Std Codes F12=Previous


.
.
CS3090?5 Build Activity Overlays 11/16/97
WORKWITH Case Activities 16:09:30

Provider.. CWS ZZZ Nursing Home Worker....... CWS
Service Children Foster Care Process 5094 Form
??????????????????????????????????????????????????????????????????????????????
_S__Activity_to_be_Performed______________Dsplmnt__P__Document_ID___Actvty_Use
_ F5094 Initiate FC payment (CPITS) 001 W 1 Y N N

...

Key any char to select an Activity to Work With or F6 to Add a new Activity.
Enter F6=Add Activity F12=Previous

.